665 ICT Infrastructure Replacement Programme PDF 94 KB
The Cabinet is requested to consider the agenda report and to make the recommendation to the Council as set out below:
Recommendation to the Council
That Cabinet recommends that Council approves the drawdown of Asset Replacement Funding (ARP) funding (£375,500) allocated for the replacement of ICT Infrastructure (SAN, Oracle).
Additional documents:
Decision:
RECOMMENDATION TO THE COUNCIL
That Council approves the drawdown of Asset Replacement Funding (ARP) funding (£375,500) allocated for the replacement of ICT Infrastructure (SAN, Oracle).
Minutes:
Mr Wilding introduced the report. Mr Mildred and Mr Forward were also present. Mr Wilding explained that over the next 12 months a number of core elements of the ICT infrastructure will reach ‘end of life’ status. He highlighted the breakdown of current equipment costs and replacement costs detailed in Appendix 1. In order to complete the Programme it will be necessary to draw down funds from the Asset Replacement Programme.
Mrs Lintill wished to note her support for the project.
Decision
The Cabinet then voted unanimously to make the recommendation below.
RECOMMENDATION TO THE COUNCIL
That Council approves the drawdown of Asset Replacement Funding (ARP) funding (£375,500) allocated for the replacement of ICT Infrastructure (SAN, Oracle).