Issue - meetings

Internal Audit - Audit Plan Progress

Meeting: 24/10/2019 - Corporate Governance & Audit Committee (Item 274)

274 Audit Reports, Progress Report - 2019-2020 Audit Plan pdf icon PDF 84 KB

The committee is requested to note performance against 2019-2020 audit plan progress report.

Additional documents:

Minutes:

Mr James introduced this item.  Mr Mildred was in attendance to answer questions relating to the Building Security follow-up, which had one recommendation still in progress.  Mr Mildred explained that he was disappointed by the audit results and outlined the steps taken that had resulted in a new process being put in place concerning the deactivation of leavers ID passes.  Mr James advised that a review of the new process would be carried out during January 2020.

 

RESOLVED

 

That progress against the 2019/20 Audit Plan be noted.