Decision Maker: Cabinet, Council
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: Yes
RESOLVED
1. The release of £11,250 of Section 106 Sport and Leisure funding for pre-construction services for Oaklands Park Artificial Grass Pitch (AGP).
2. The appointment of contractor E as set out I appendix one to undertake the pre-construction services and subject to partnership funding being secured, enter into a contract for the delivery of the AGP as the preferred contractor for the Oaklands Park football pitch project.
*RECOMMENDED TO COUNCIL
The release of a further £288,750 of section 106 Sport ad Leisure funding, towards a total project cost of £1,210,800, as the council’s contribution towards the delivery of the Artificial Grass Pitch (AGP) at Oaklands Park, Chichester. This funding being conditional on partnership funding being achieved to cover the full costs of the project.
Report author: Mrs Sarah Peyman
Publication date: 08/09/2022
Date of decision: 06/09/2022
Decided at meeting: 06/09/2022 - Cabinet
Effective from: 15/09/2022
Accompanying Documents: