The Cabinet is requested to consider the report and make the following resolution:
That the update summary of the progress made in signing the Development Agreement in section 4.9 and the site acquisitions summary in section 4.10 be noted and the actions as set out in the proposal, section 6, of the report be approved.
Additional documents:
- Restricted enclosure 2 , View reasons restricted (42/2)
Decision:
RESOLVED
1. That the update summary of the progress made in signing the Development Agreement in section 4.9 and the site acquisitions summary in section 4.10 be noted.
2. That section 6.3 of the report be removed with the remaining actions as set out in section 6 of the report approved.
Minutes:
Cllr Lintill left the meeting and the Chair passed to Cllr Taylor.
Cllr Dignum introduced the item.
Mrs Hotchkiss explained that section 6.3 would no longer be required. Cllr Dignum agreed with the suggestion to delete recommendation section 6.3.
Mr Hotchkiss responded to questions from Cllr Bell and Cllr Plant.
In a vote the following resolutions including amended recommendation 2 were agreed:
RESOLVED
1. That the update summary of the progress made in signing the Development Agreement in section 4.9 and the site acquisitions summary in section 4.10 be noted.
2. That section 6.3 of the report be removed with the remaining actions as set out in section 6 of the report approved.