Infrastructure Business Plan

Meeting: 08/09/2020 - Cabinet (Item 33)

33 Approval of the draft Infrastructure Business Plan 2021-26 for consultation (with the City, Town and Parish Councils and key Infrastructure Delivery Commissioners) pdf icon PDF 394 KB

The Cabinet is requested to consider the report and make the following resolution:

 

That the Draft Infrastructure Business Plan 2021-26 (Appendix 1) be approved for consultation (with the City, Town and Parish Councils, neighbouring local authorities including the South Downs National Park Authority and key infrastructure Delivery Commissioners) for a period of six weeks from 5 October to 16 November 2020.

Additional documents:

Decision:

RESOLVED

 

That the Draft Infrastructure Business Plan 2021-26 (Appendix 1) be approved for consultation (with the City, Town and Parish Councils, neighbouring local authorities including the South Downs National Park Authority and key infrastructure Delivery Commissioners) for a period of six weeks from 5 October to 16 November 2020.

Minutes:

Cllr Taylor introduced the item. She drew attention to the following funding allocations:

 

·         The removal of IBP 398, funds originally allocated for 2020/21 as per paragraph 3.9 of the report and its replacement by projects set out in paragraph 3.16 of the report.

·         The addition of IBP 840, £60,000 allocated for 2021/22

·         The addition of IBP 841, £500,000 allocated for 2022/23 delivery

·         The addition of IBP 593, £2.1 million allocated for 2025/26 delivery

·         The addition of IBP 842, officers have requested £575,000 over 5 years

·         The addition of IBP 844, officers have requested £880,000 for 2022/23

 

In a vote the following resolution was agreed:

 

RESOLVED

 

That the Draft Infrastructure Business Plan 2021-26 (Appendix 1) be approved for consultation (with the City, Town and Parish Councils, neighbouring local authorities including the South Downs National Park Authority and key infrastructure Delivery Commissioners) for a period of six weeks from 5 October to 16 November 2020.

 


 