Decision details

Increasing the provision of the Council's Temporary Accommodation at Freeland Close, Chichester

Decision Maker: Cabinet

Decision status: Noted

Is Key decision?: Yes

Is subject to call in?: No

Purpose:

That following planning approval for this development, an order is placed with Southern Gas Network (SGN) for the relocation of a gas pipeline, ahead of the main contract.

That the Council approves the allocation of up to £120,000 from the Housing Investment Reserve to meet the cost of this work.

Decision:

*RESOLVED

 

1.     That an order is placed with Southern Gas Network (SGN) for the relocation of the gas pipeline, shown in Appendix 1.

2.     That Cabinet approves the allocation of up to £120,000 from the Housing Investment Reserve to meet the costs of this work, subject to the urgency procedure (as set out in para 5.2 of the report).

3.     That delegated authority is given to the Director of Housing and Communities to make changes to the Project Initiation Document (PID), in consultation with the Cabinet Member for Housing, to accommodate approval of a final design and submission of planning application.

4.     That members note the delay in the programme as set out in section 5.4 of the report.

 

RECOMMENDATION TO THE COUNCIL

 

That the urgent decision for Cabinet to approve the allocation of up to £120,000 from the Housing Investment Reserve to meet the cost of this work be noted.

Report author: Mrs Linda Grange

Publication date: 03/10/2019

Date of decision: 01/10/2019

Decided at meeting: 01/10/2019 - Cabinet

Accompanying Documents: