Decision details
Resurfacing, Improved Drainage and additional site enhancements at Westhampnett Depot
Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
To seek cabinet approval for an increase in the budget to accommodate the provision for electric vehicle charging and a water capture system at the Westhampnett site as part of the developing work programme.
Decision:
*RESOLVED
1. That Cabinet approves the inclusion of environmental and operational enhancements to the scheme set out in section 5, subject to Council’s approval of the additional costs.
2. That Cabinet approves the appointment of Contractor B for undertaking the resurfacing, improved drainage, environmental and operational enhancements and associated work at CCS Depot, and delegates authority to the Director of Corporate Services to conclude the detail of the contract following consultation with the Cabinet member for the Environment and Contract Services
RECOMMENDATION TO COUNCIL
That Cabinet recommends to Council to increase the budget from £592,000 to £850,000 of which £650,000 funded from reserves and £200,000 funded from the Asset Replacement Programme to enable the inclusion of additional works as set out in Section 5.
Report author: Mr Kevin Carter
Publication date: 05/12/2019
Date of decision: 03/12/2019
Decided at meeting: 03/12/2019 - Cabinet