Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
The Public are likely to be excluded from any
discussion at which this report is considered on the grounds that
it is likely that there would be a disclosure to the public of
‘exempt information’ of the description specified in
Paragraph 3 (Information relating to the financial or business
affairs of any particular person (including the authority holding
that information)) of Part I of Schedule 12A to the Local
Government Act 1972.
RESOLVED
1) Having considered the tender report (Exempt Appendix) prepared by Pope Consulting Limited, that the existing three Combined Heat and Power units be replaced with a single unit under a capital purchase (CAPEX) scheme.
2) That Tenderer 2 be approved as the preferred bidder, subject to the application of sensitivity analysis to the bid.
3) That the balance of the existing budget (amounting to circa £115,000) be released for the replacement of the three existing gas engines and that an additional £80,000 be released from capital reserves to fund the new CHP and associated costs and fees.
Report author: Mr John Bacon
Publication date: 09/07/2015
Date of decision: 07/07/2015
Decided at meeting: 07/07/2015 - Cabinet
Effective from: 16/07/2015